DOWNTOWN CAMBRIDGE MAIN STREET RECONSTRUCTION

Union Gas utility upgrades are required to be completed in advance of the City's project. Proposed utility relocations are planned from 72 - 151 Main Street including Mill Street and a portion of Lutz Street.

Aecon, a Union Gas contractor, is scheduled to begin utility relocations on April 1, 2019, and is expected to take approximately 6-weeks to complete.

 

The City's contract is expected to be awarded the Main Street Reconstruction & Streetscaping Project on April 22nd, 2019.

 

Brief timeline of the four (4) phases for the project:

 

April 1, 2019 - Union Gas/Aecon to begin utility relocations

May 10th, 2019 - Union Gas/Aecon to complete utility relocations (approximate)
May 13, 2019 - Contractor retained by the City of Cambridge to begin Main Street Reconstruction and Streetscaping project. (approximate)

End of September 2019 - Main Street Reconstruction and Streetscaping complete

Main Street Reconstruction and Streetscaping Project Phasing:

Phase 1A - Main Street from Ainslie St. North to Wellington St. South (Union Gas Work)
Phase 1B - Main Street from Ainslie St. North to Wellington St. South (City's Contractor)
Phase 2 - Intersection of Main Street and Wellington St. South (City's Contractor)
Phase 3 - Wellington St. South to Shade Street (City's Contractor)

 

For a more information on this project, please visit www.cambridge.ca

 

 

ABOUT US

Historic Galt, better known as Downtown Cambridge, boasts a wide selection of incredible shops, restaurants, and services set against a uniquely picturesque landscape.

  • White Facebook Icon
  • White Twitter Icon
  • White Instagram Icon
CONTACT US

MailP.O. Box 1723

Station Galt 
Cambridge, Ontario N1R 7G8

‚Äč

 

Email: info@downtowncambridgebia.ca

SUBSCRIBE TO OUR 
MONTHLY NEWSLETTER

© 2018 All Rights Reserved Downtown Cambridge Business Improvement Area | Created and Managed by B. Wallace Kennedy Production Management Inc.